Power ministry hastens rural electrification plans after Modi’s I-Day speech

power-generation

Following Narendra Modi’s Independence day speech Power ministry has decided to electrify remaining  7,876 un-electrified villages before 1st May 2018.

The project, which was taken on mission mode last year, will now see squeezing the implementation schedule to 12 months and also dividing village electrification process into 12 stages, with defined time lines for monitoring.

Modi on his  Independence day speech said: “Out of 18,000 un electrified villages (as per Census 2011), more than 10,000 villages have been electrified and I have been told they are with us, watching this celebration of Independence Day.”

The government of India took the rural electrification project on ‘mission mode’ in August 2015, and increased the rate of roll out.

While only 1,654 villages were electrified during the 4.5 months starting from April 2015 to 14 Aug last year, a total of 8,397 additional villages were electrified from 15th August 2015 to 14th August 2016.

And the pace of roll-out has been increasing. Last week, a record 398 villages were electrified under Deen Dayal Upadhyaya Gram Jyoti Yojna (DDUGJY), the Power Ministry said.

In order to expedite the progress further, a close monitoring is being done through Gram Vidyut Abhiyanta (GVA) and various actions are also being taken on regular basis like reviewing the progress on monthly basis, it added.

It also has a website dedicated to tracking the project.

Follow ULTRA.news
BHEL wins Rs 2,800 cr order from MAHAGENCO One of BHEL's projects Bharat Heavy Electricals Limited (BHEL) said it won a Rs 2,800 cr order from Maharashtra State Power Generation Company (MAHAGENCO) to set up a 660MW coal-based thermal power project in Bhusawal Thermal Power Station in Maharashtra. It will be set up...
SOLAR MISSION: It’s another nail-biter for India in 2017-18 India faces steep odds in its race to meet its solar power addition targets for the current year. Last year, the country had added only 5.53 GW of incremental solar power capacity against a target of 6 GW. This year, the target is 10 GW. However, as of November end, it has...
India seeks “viable project proposal” from Westinghouse for AP nuclear plant The government of India said there was no change in its plans to set up a mega nuclear plant in Kovvada in Andhra Pradesh with bankrupt US technology provider Westinghouse. However, said the Department of Atomic Energy, the two parties are yet to arrive a "viable project prop...
BHEL wins massive Rs 7,300 cr order from TANGEDCO Bharat Heavy Electricals Limited said it won a Rs 7,300 cr order to set up a 1,320 MW Supercritical Thermal Power Project (TPP) in Tamil Nadu. Valued at over Rs.7,300 Crore, the order for setting up the 2x660 MW Udangudi TPP has been placed on BHEL by Tamil Nadu Generation an...
India to see 6 GW of wind power auctioned in 5 months Inox Wind Limited, the most aggressive player in bidding for new wind power projects, said it expects almost 6 GW of new wind power projects to be auctioned in India over the next five months. In comparison, the country added 5.4 GW of wind power capacity on the ground in the...
No salvation in sight for gas-based power plants – India Ratings India Ratings, a Fitch company, said it sees no chance for a revival in the fortunes of natural gas-based power generation plants in India. The country saw the setting up of several such plants, especially in Andhra Pradesh, at the turn of the century on expectations of a gas...
South India still water-stressed despite decent monsoon Despite a decent monsoon season, water levels at storage facilities in India continues to be below those of last year as well as the 10-year average. Of particular concern is the situation in South India, only 39% of the total capacity of the reservoirs has been filled so far...
India achieves only 14% of rooftop solar power target Even as India more or less sticks to the target on adding large solar farms under its ambitious Solar Mission project, the other leg of the plan -- rooftop solar -- remains woefully behind target. Under the solar mission, India is supposed to have put in 5,000 megawatt of sola...
Surya introduces 32-watt full-size ceiling fan with BLDC technology Surya Roshni, one of India's oldest electrical brands, said it launched what could be India's most power efficient full-size ceiling fan -- the SS-32. The fan belongs to the new breed of brushless or BLDC fans that use an electronic circuit to convert alternating current into ...
BHEL wins 15 MW solar project, total reaches 180 MW Bharat Heavy Electricals Limited said it got an order from Gujarat Alkalies and Chemical Limited for setting up a 15 MW Solar Photovoltaic power plant in Gujarat on Engineering, Procurement and Construction (EPC) basis. This takes the total solar power generation capacity bein...
India enters the nuclear power club with new 7.7 GW program Koodankulam Plant built with Russian help India today announced among the biggest civil nuclear programs anywhere in the world, saying it will set up 7,700 MW of indigenously developed nuclear power plans. It is the first time that the country is creating so much capacity ...
NTPC starts 660 MW Solapur Super Thermal Power Project in Maharashtra One of NTPC's thermal plantsNTPC Ltd, India's largest power producer, has taken its total installed production capacity beyond the 51,000 MW mark with the addition of the 660 MW Solapur Super Thermal Power Project in Maharashtra. The total capacity of the NTPC Group has b...
Maharashtra gets 65% of all National Highway upgrades in FY17 Even as states race to denotify state highways as 'urban roads', Maharashtra, home of roads and highways minister Nitin Gadkari, managed to get 65% of all sanctioned upgrades of state highways into national highways last year. According to year-end data prepared by the roads a...
BHEL commissions 800 MW supercritical coal unit in Karnataka The Raichur plant Bharat Heavy Electricals Limited (BHEL) commissioned an 800 MW coal-based supercritical thermal unit at the  Yeramarus Thermal Power Station located in Raichur district of Karnataka, the heavy equipment maker said. The plant is a joint venture between BHE...
India is the first country to reuse nuclear waste on large scale – Minister A rally to popularize nuclear power in Mumbai in 2014 The Department of Atomic Energy today said that India is the first country in the world where the waste produced by nuclear power plants is being used for civilian applications. Jitendra Singh, the minister of state ove...
Govt not to supply LNG to stranded gas power projects from next month A gas-based power plant owned by Tamil Nadu Govt The government is not planning to extend the two-year-old scheme to supply subsidized, imported natural gas to stranded gas power projects when it expires this month, according to a senior power ministry official. "We got a ...
India to add 34.5 GW of hydroelectric capacity in 10 years A hydro-power plant in Himachal Pradesh India will set a target of adding 34.5 GW of hydro-power generation capacity in the next ten years, according to power ministry sources. "The target for the 13th plan has been set at 13.31 GW and that for the 14th plan will be 21.15 ...
NTPC achieves 12th Five Year plan targets, adds 12.84 GW in five years One of NTPC's several power plants National Thermal Power Corporation said it has achieved, and exceeded, its target for the addition of power generation capacity in the 12th five-year plan by adding 1,070 MW today. Three new units were added today -- one of 800 MW at Kudg...
Can’t allow NGOs to impede India’s growth: Center to NHRC Women from the Mahan region celebrate after cancellation of coal blocks.Greenpeace helped organize protests against open coal mining in the area. The home ministry has written back to the National Human Rights Commission that non-governmental organizations cannot be allowed t...
After missing twice, India comfortably meets power sector targets for 12th five-year plan After missing its targets by wide margins in the previous two five-year plans, India is all set to comfortably meet or exceed all its power sector targets for the 12th five-year plan that ends this month. Five-year plans, borrowed from the Soviet Union, are a legacy of Nehruvi...