After missing twice, India comfortably meets power sector targets for 12th five-year plan

After missing its targets by wide margins in the previous two five-year plans, India is all set to comfortably meet or exceed all its power sector targets for the 12th five-year plan that ends this month.

Five-year plans, borrowed from the Soviet Union, are a legacy of Nehruvian policy of setting development targets every five years.

Though state enterprises were supposed to play a pivotal role in the execution of such plans, it is the private sector players who have helped change the dismal track-record of the power sector in achieving the targets.

With several ‘mega’ and ‘ultra mega’ power projects from private companies such as Reliance Infrastructure coming online in the past few years, the generation target for 12th plan period — which ends this month — has been easily achieved.

For the power sector as a whole, there were three specific targets — in generation, transmission and transformer capacity, and all three are being met. However, there are sub-segments — such as large hydro and renewables — that missed.

The target for total power generation capacity addition was 88,537 megawatt. With one month left to go, a total of 94,689 megawatt of fresh power capacity has already been added thanks to enthusiastic participation from private players.

Against a target of 43,500 MW, private players have added over 60,000 MW, while the central government undertaking NTPC is chasing a target of 11,920 MW for what looks set to be a close finish.

TRANSMISSION

The target for transmission was to add 1.07 lakh circuit km, and 1.06 ckm has already been added as of January.

Similarly, the target for total transformer capacity addition was 2.85 lakh mega volt amps. The industry has already added 3.04 lakh with two months to spare.

In comparison, India added generation capacity of 50,000 MW (50 GW) — well short of the targeted 62 GW.

In the preceding, 10th five-year plan, the target was 41,110 MW and the achievement was a mere 20,950 MW.

MISSES

However, nearly all of the incremental generation capacity has come in the thermal category, with large hydro-power missing its target spectacularly.

A total of 10,897 MW of incremental hydro-power capacity was supposed to be added, but the achievement so far is only around 4,000 MW.

Another big miss is on renewables — which doesn’t include big hydro for this purpose.

These were supposed to account for an incremental generation capacity of 30,000 MW, but actual achievement was only 22,736 MW with two months to spare.

The target for total installed solar energy is 12,700 MW by the end of this month. But as of last year, the country was adding only 1,000 MW per quarter and had an installed base of only 9,000 MW at the end of December.

Solar is likely to pick up the slack in coming months as several mega projects have been approved in recent months and will come online in the coming quarters.

THIRTEENTH PLAN

The thirteenth plan period is unlikely to see the kind of additions in conventional generation capacity witnessed in the 12th period due to the rise of renewables.

Against a total coal-based capacity of 250 GW built over several decades, India is estimated to have a potential of 750 GW in solar and over 300 GW in wind power. However, at present, only 10 GW of solar and 29 GW of wind power capacity has been realized.

Meanwhile, another 70 GW of coal and 13 GW of large-hydro projects are at various stages of development.

It is believed that India will use some of the planned new coal-based capacity to retire its less inefficient, legacy coal plants rather than to increase its total output.

The 13th plan period is also likely to see a higher participation from the private sector in bringing more hydro power capacity online. Several large and medium-sized hydro power projects, such as the Ratle 850 MW project in Jammu & Kashmir and the Teesta 500 MW project in Sikkim are under construction in the private sector (see chart).

Follow ULTRA.news
JSPL wins 0.5 mtpa coal linkage for captive power plants Jindal Steel and Power said it secured coal linkages of 511,000 tonnes per year in a recently concluded auction for the use of its captive power plants.Angul plant of JSPL"The coal linkages, secured for a 5-year duration, will provide steady supply of fuel to captive po...
IREDA to sell 14 cr shares in IPO to help meet India’s renewable targets The central government has okayed the listing of India's premier renewable energy agency, IREDA, via an initial public offer.Part of IREDA co-financed 202.40 MW Wind Power Project in APThe move will help the non-banking finance company "increase its equity base which wil...
India enters the nuclear power club with new 7.7 GW program Koodankulam Plant built with Russian helpIndia today announced among the biggest civil nuclear programs anywhere in the world, saying it will set up 7,700 MW of indigenously developed nuclear power plans.It is the first time that the country is creating so much capacity ...
Indian IT industry facing layoffs as conditions worsen, warns Assocham Trump unveiled his 'Buy American, Hire American' program yesterdayIndian IT companies are bound to see "some laying off" of their work force back home due to various negative forces impacting the industry, Assocham -- an association of various industries -- warned."With ...
NTPC starts 660 MW Solapur Super Thermal Power Project in Maharashtra One of NTPC's thermal plantsNTPC Ltd, India's largest power producer, has taken its total installed production capacity beyond the 51,000 MW mark with the addition of the 660 MW Solapur Super Thermal Power Project in Maharashtra.The total capacity of the NTPC Group has b...
Maharashtra gets 65% of all National Highway upgrades in FY17 Even as states race to denotify state highways as 'urban roads', Maharashtra, home of roads and highways minister Nitin Gadkari, managed to get 65% of all sanctioned upgrades of state highways into national highways last year.According to year-end data prepared by the roads a...
Rs 1.7 lakh cr deposited via demonetization may not be withdrawn – SBI Monthly cash withdrawals for all banks | source:SBI ResearchThe Indian banking system is likely to get a permanent liquidity boost of Rs 1.7 lakh cr due to the demonetization of high-denomination bank notes, State Bank of India chief economic adviser said in a note to bank c...
BHEL commissions 800 MW supercritical coal unit in Karnataka The Raichur plantBharat Heavy Electricals Limited (BHEL) commissioned an 800 MW coal-based supercritical thermal unit at the  Yeramarus Thermal Power Station located in Raichur district of Karnataka, the heavy equipment maker said.The plant is a joint venture between BHE...
India is the first country to reuse nuclear waste on large scale – Minister A rally to popularize nuclear power in Mumbai in 2014The Department of Atomic Energy today said that India is the first country in the world where the waste produced by nuclear power plants is being used for civilian applications.Jitendra Singh, the minister of state ove...
Govt not to supply LNG to stranded gas power projects from next month A gas-based power plant owned by Tamil Nadu GovtThe government is not planning to extend the two-year-old scheme to supply subsidized, imported natural gas to stranded gas power projects when it expires this month, according to a senior power ministry official."We got a ...
India to add 34.5 GW of hydroelectric capacity in 10 years A hydro-power plant in Himachal PradeshIndia will set a target of adding 34.5 GW of hydro-power generation capacity in the next ten years, according to power ministry sources."The target for the 13th plan has been set at 13.31 GW and that for the 14th plan will be 21.15 ...
NTPC achieves 12th Five Year plan targets, adds 12.84 GW in five years One of NTPC's several power plantsNational Thermal Power Corporation said it has achieved, and exceeded, its target for the addition of power generation capacity in the 12th five-year plan by adding 1,070 MW today.Three new units were added today -- one of 800 MW at Kudg...
Can’t allow NGOs to impede India’s growth: Center to NHRC Women from the Mahan region celebrate after cancellation of coal blocks.Greenpeace helped organize protests against open coal mining in the area.The home ministry has written back to the National Human Rights Commission that non-governmental organizations cannot be allowed t...
India stockpiles crude oil worth Rs 4,258 cr as strategic reserve Undated government photo of construction work at one of the tanksIndia has filled a little over one-third of its phase 1 'strategic oil reserve' at a cost of Rs 4,258 cr, about $640 mln.The country is in the process of building five underground reserve facilities for cru...
Maharashtra gets 50% of India’s total highway budget this year Maharashtra, home state of Nitin Gadkari, accounted for 50% of the new highway development projects sanctioned in the ongoing financial year, data from the ministry of road transport and highways showed.A total of 520 new projects -- including expansions -- worth Rs 53,264 cr...
Solar power output up 75% this year, but still only 1% of total Solar, wind in India's total power production 2016-17Production of electricity from solar power is all set to rise 75% this year, while that from wind is on track to rise 51%, according to the latest numbers available with the ministry of new and renewable resources, governm...
India plans for eight-fold increase in nuclear power capacity to 45 GW File photo Koodankulam Nuclear PlantIndia is planning to increase its nuclear power generation capacity to 44,628 megawatt, about eight times the current capacity of 5,780 MW, the Prime Ministers' Office said today.At present, India has seven nuclear power plants. Howeve...
Wholesale price inflation hits 3-year high on high diesel prices High fuel prices, particularly that of diesel, lifted India's wholesale price index to its highest level since the Narendra Modi government took power almost three years ago.On an overall level, wholesale price of various items jumped 6.55% in February when compared with ...
No immediate plans for universal basic income: Indian Government India's welfare budget, 2016-17The Indian government has no immediate plans or proposals to institute a scheme of 'unversal basic income' in place of the myriad social welfare scheme run by the country at present, the finance ministry said in response to a query.The clar...
Gadkari to miss ambitious highway target for 2016-17 Nitin Gadkari, who is slowly building up a reputation as a pragmatic and capable minister, is likely to face major disappointment in the ongoing financial year as his ministry is unlikely to meet the steep road construction target it set for itself.Unlike the term of the ...
Poor water levels cripple hydropower generation in Telangana, Jharkhand, Andhra, TN Water levels of dams in central and south India are abnormally low this year, going by data of hydro-electricity production across India.According to data of electricity produced by dams in India from April 2016 to February 2017, both the south and central India are facing ex...
Half of rural population classified as poor in Socio-Economic Caste Census Half of India's rural population have been classified as poor by the Socio-Economic Caste Census of India 2011, the government said today.The findings of Socio-Economic Caste Census of India, which was conducted after vociferous demands by some political parties, has never be...
Power companies to save Rs 2,500 cr/yr as coal linkage rationalization expands The amount of money estimated to be saved by power companies in India due to the rearrangement of coal supplies has risen to Rs 2,503.50 cr per year, according to power ministry sources.The program of swapping coal sources, known as 'coal linkage rationalization', is in its t...
Chhattisgarh leads as India uses solar to take power to villages New villages electrified in India, year-wiseThe central Indian state of Chhattisgarh has come out as a leader in India's quest to take electricity to remote villages where grid-based power cannot be supplied due to economical reasons.The state accounts for 550 of the 852...
ABB sells 4.5 GW of wind power generators in India ABB, one of the world's biggest manufacturers of large electrical equipment, said it crossed the 4.5 GW milestone in terms of sales of wind power generators in India, and that the country is likely to add 4 GW of capacity this year.India has a target of having 60 Gigawatt of ...